Marquee projects

Government · Sacramento

State Capitol Annex

Led BIM/VDC delivery on a large-scale electrical scope with a team peaking at 15 — coordination, modeling, shop and prefabrication drawings from underground utilities through commissioning.

53% profit margin — above benchmark

Civic · Sacramento

Superior Courthouse

Ran a multimillion-dollar, 30+ month build with a 12-person team: team leadership, client-side management, estimation and bid strategy, and BIM coordination throughout.

38% profit margin — above benchmark

Healthcare · Sacramento

Sutter Health, J Street

Active hospital project inside a portfolio of eight — client relations, financial and schedule accountability, with hands-on Revit work where the scope needs technical depth.

In progress · Late 2025 –

Life sciences · Foster City

Gilead Sciences facility

Life sciences scope carried alongside the healthcare portfolio, with cross-team oversight of coordination and delivery against a demanding schedule.

In progress · Late 2025 –

02

Progression · Sanveo, Inc.

2018 → present

Six roles, one company. Each step added scope without giving up the modeling work underneath it.

Senior Project Manager

Portfolio ownership across healthcare, life sciences, and civic 2024 —

Project Manager

Capitol Annex electrical scope, team of 15 2023 — 24

Assistant Project Manager

First full P&L: the Courthouse, start to finish 2022 — 23

Senior Project Engineer

Schedule, budget, and RFIs on a two-year build 2021 — 22

BIM Construction Engineer

Revit modeling, Navisworks coordination, 3 detailers 2018 — 21

Intern

QA/QC on models and markups, clash review 2018

Full dates, scope, and metrics are in the résumé PDF.

03

How I work

I stay in the model

Managing eight jobs doesn't mean losing the details. When a scope gets difficult I open Revit myself — it keeps my estimates honest and my detailers trusting me.

Margin comes from coordination

The profit on a job is decided long before installation. Clashes caught in Navisworks, prefab drawings that field crews can build from — that's where the numbers come from.

Right-size the team

I've scaled a team to fifteen and pulled a structure back when it added layers instead of output. Both were the right call at the time.

04

Capability

Leadership

Hands-on technical leadership · Project & team management · Multi-project portfolio oversight · Stakeholder management · Financial & schedule accountability

Technical

Autodesk Revit · Navisworks Manage · Revizto · BIM coordination & clash detection · Electrical trade coordination · QA/QC · MS Project

Sectors & credentials

Healthcare · Life sciences · Government & civic · OSHA 30-Hour · LEED Green Associate

05

Education

MS, Construction Management

California State University, East Bay

2018

BE, Civil Engineering

Visvesvaraya Technological University

2015

Open to VDC leadership roles in the Sacramento region.

Happy to talk through portfolio scale, coordination workflow, or how a scope gets from underground utilities to commissioning.